Manuals / Project Management for Tech / Chapter 5
B · People & risk · intermediate · ~40 min · Chapter 5 of 9
RAID: risks, assumptions, issues, decisions
A living RAID log beats a risk slide that died in week one. Risks have owners, triggers, and mitigations.
Path progress50%
Step 1 of 2
Start the RAID
Risks = maybe. Issues = now. Assumptions = believed true. Decisions = locked choices with date/owner.
Example
Risk | Prob | Impact | Owner | Trigger | Mitigation | Status
Issue | Owner | Impact | Next action | Due
Assumption | Owner | Validate by | Status
Decision | Date | Decider | Alternatives consideredDo this now
Create a RAID table with at least 3 risks, 2 assumptions, 1 open issue, 2 decisions.
Was this step clear?
Chapter learning outcomes
- Risk vs issue
- Probability × impact
- Decision log
Clear these before you leave
Side quest
Weekly RAID hygiene
Update RAID once this week in a real standup or async note.